Homework Test
Quiz 1
Question
1. Construct the network of diagram
2. Find the critical path from the diagram.
The critical path for the diagram is
= A(3) + BC(2) + DF(3) + G(1)
= 9 days
Question
1. Construct the network of diagram
2. Find the critical path from the diagram.
The critical path for the diagram is
= A(3) + BC(2) + DF(3) + G(1)
= 9 days
Labels:
Project Management - Quiz 1